As the demand for high-speed internet escalates, particularly in underserved regions, the deployment of broadband infrastructure faces multifaceted challenges. Key among these are issues concerning rights-of-way (ROW), pole attachments, and environmental permitting. Addressing these obstacles is crucial for stakeholders aiming to enhance broadband accessibility efficiently.
Rights-of-Way Challenges
Rights-of-way refer to the legal rights to pass through property owned by another party, essential for installing broadband infrastructure along roads, utility lines, and other public or private properties. Navigating ROW access involves complex negotiations with multiple entities, including federal, state, and local agencies, each with distinct regulations and requirements. The Federal Highway Administration (FHWA) has been directed to facilitate the deployment of broadband within the right-of-way (ROW) of highways to reduce barriers in underserved communities.
To streamline ROW access, some states have enacted multipurpose statutes granting telecommunications and public utilities access under existing agreements. For instance, Oklahoma’s House Bill 1965 allows electric utilities to use existing easements for broadband installation, a model adopted by at least 22 other states.
Pole Attachments
Deploying broadband often necessitates attaching cables or equipment to existing utility poles. The process involves negotiating access with pole owners—typically electric or telecommunications companies—and addressing costs, safety considerations, and regulatory compliance. The Federal Communications Commission (FCC) oversees pole attachment regulations, but states can opt to self-regulate. As of 2016, twenty states have maintained their right to self-regulate utility poles.
The “One Touch Make Ready” (OTMR) policy has emerged as a strategy to expedite pole attachment processes. OTMR allows a single construction crew to perform all necessary adjustments on a utility pole, reducing delays associated with sequential work by multiple entities. Cities like Louisville, Kentucky, and Nashville, Tennessee, have implemented OTMR ordinances to facilitate the faster deployment of broadband.
Environmental Permitting
Broadband projects must comply with environmental regulations, including assessments under the National Environmental Policy Act (NEPA). These evaluations consider potential impacts on historic sites, endangered species, and other environmental factors. While essential for conservation, the permitting process can be time-consuming and complex. The National Telecommunications and Information Administration (NTIA) acknowledges these challenges and has developed toolkits to help stakeholders navigate environmental permits.
To address these challenges, various strategies have been proposed and implemented:
-
Dig Once Policies: Coordinating infrastructure projects to install broadband conduits during other construction activities minimizes the need for repeated excavations, thereby reducing costs and environmental disruption.
-
Standardized Permitting Processes: Developing uniform applications and procedures across jurisdictions can alleviate confusion and expedite approvals. For example, Virginia mandates a 45-day timeline for ROW application decisions, promoting timely responses.
-
Enhanced Coordination: Early engagement with transportation agencies, environmental bodies, and utility companies can preempt potential obstacles, facilitating smoother project execution.
Expanding broadband infrastructure in underserved areas is imperative for bridging the digital divide; however, challenges related to rights-of-way, pole attachments, and environmental permitting present significant hurdles. By adopting streamlined policies, fostering inter-agency collaboration, and implementing innovative solutions like OTMR, stakeholders can mitigate these challenges, paving the way for more efficient and widespread broadband deployment.